Hi André,
I have a PO which was created through a PR. However, when I check the budget control statistics under encumbrance, it shows 2 lines for the same PO even though the PO has only 1 line. Also, both lines in the encumbrance show status as confirmed. This is resulting in the double amount to be reserved. Is there anyway to remove/relieve 1 line from the encumbrance?