Hi Thomas,
Further to add to what i mentioned above, if i directly 'assign' the resource in the WBS, then i was still able to create this discrepancy between the 'Booked' and 'Assigned' hours. Ideally, if the resource is assigned to a task, it should automatically be booked. But this is not happening it seems. Please see the screenshot below. This testing is done in update 12.
Please correct if i am wrong, my assumption is:
Booked hours - Hours for which resource is booked on the project
Assigned hours - Hours for which resource is assigned to a particular task on the project
So ideally Booked hours can be greater than Assigned hours, as there may be a case where the resource is not assigned to a task but just booked to the project. But Assigned hours can never and SHOULD NEVER be greater than Booked hours because when the resource is assigned to the task of a project, he / she is ideally booked for the same project as well. This logic seems to be broken in the product.
Kind Regards
Sarang