Hi,
I have two questions-:
1. How can have D365 to create a Job Card Journal automatically at the start of the Production Order, like how we create Route Card Journal at the Start of Production Order. Do we have to create it manually since User decides what operations have to start when and by which Worker? Does Job card Terminal / Job Device help in any way?
2. How can I setup the operations in such a way that I cannot move the next operation without finishing the previous operation? Is using the "Link / Link Type", if so what would be setup for that?
Example
Operation 10 (Next 20)
Operation 20 (Next 30) (should not even start this operation until operation 10 is complete)
Operation 30
Regards,
Narasimha