In AX 2012 R2 CU 7 I created a project type Internal. I posted some 'Hour' and 'Expense' transactions. Then I used standard functionality 'Change Project Group'. I chose the group related to project type 'Time & Material'. I inserted Project Contract and started action. Finally I've got the following results:

1. Project type was changed;

2. Project Group was changed;

3. Posted transactions were related to the project still;

4. I couldn't create Invoice Proposal based on existing transactions.

After short investigation - I concluded that relation to Funding Sources is broken in some project transaction tables. Is it bug of such version  - or - is it standard behavior of AX ? (I checked the same results on AX 2012 R3 :( ). 

Looking forward for any experiences/suggestions...