Hello,
we have some problems with the BOM LEVEL and the Master Scheduling.
F.E. you have a article A with an Bom.
The Article A (BOM Header) has the Bom Level 1
The Article B (BOM Position) has the Bom Level 1
The Bomversion is not activated but approved.
The MRP know don´t calculate a planned Production/purchase order for Article B.
The MRP will only calculate the Article B, when you do the following:
1. Activate Bom Version
2. JOB Recalc Bomlevels
3. Master Scheduling
Does anyone know this issue?