Hi All
We are in the process of implementing and improving our MRP production planning. Currently we use Finite capacity for when we do the Job Scheduling (using Priority-Delivery Date Sorting and direction as Forward from scheduling date).
This works generally very well if we have sufficient capacity to execute the plan. However if capacity is insufficient planner would often like to schedule overtime. I could not find an easy way of doing it rather than go and manually change the calendar for the specific Work Centre to allow more working hours on that day. I wonder if it is the best way of doing it (and this is how other members of the community do it) or there are other better ways.
Thank you in advance for your advice!