RE: How to set up the capacity in the resources

$
0
0

Hi,

You set capacity against a resource, e.g. Worker 1 = 8 hours a day

Working calendar is the hours in which the resource can work within, e.g. Tuesday = 8 hours, Wednesday = 8 hours.

So for example, if there's an operation that takes 16 hours, Worker 1 will be scheduled to 8 hours on Tuesday, and then complete the job with the available 8 hours on Wednesday.. abiding by the working calendar.

The working calendar is applicable to individual resources, in the example you detailed above there would never be a 40 hour day, but 5 resources with 8 hours of their own working calendar available everyday.

Once scheduled, you can check these capacity load on the resource form.

I hope this helps