I have a requirement were we need to run forecast and mps plans for a 3 month period (3 month plan) nightly. We also need to run 12 month plans at least once a week. The settings on the coverage groups are set to align with the 3 month plans (coverage time fences, negative days positive days, explosion time fence....). When we run the 12 month plans, the planning is limited by the setting on the coverage groups aligned with the 3 month plans (even though the forecast and master plans for the 12 months have the 365 days time fences). There are no planned orders beyond the setting supporting the 3 months coverage groups.
I have two questions, 1) if I set the coverage groups time fences and negative days to align with the 12 months plans, what are the implications or risks and 2) is there a better way to achieve our goal?
Thank you